Schools

We continue to maintain an active work program for K-12 and university education facilities throughout Texas. Our work program ranges from serving as mechanical contractor on new 250,000+ SF high schools to fast-tracking renovations and central plant upgrades.

Name Location Type
Description
Teasley Lane High School Denton, TX New High School
Moises Molina High School Dallas, TX New High School
Creekview High School Carrollton, TX New High School
A.C. New Middle School
Balch Springs, TX
Expansion
Allen Senior High School Allen, TX Expansion
Lewisville Elementary #38
Carrollton, TX New School
Rockwall-Heath High School
Rockwall, TX
New School
University of North Texas Denton, TX Convention/Dining Center
South Texas Community College McAllen, TX New Thermal Energy Plant  
University of Texas Dallas, TX New Activities Center  


Project: Teasley Lane High School
Location: Denton, Texas
Type: New High School
Description:

General Contractor: Charter Builders, Ltd. - Dallas, Texas New 5A High School for Denton ISD

Project: Moises Molina High School
Location: Dallas, Texas
Type: New High School
Description:

General Contractor: Centex Construction - Dallas, Texas First new major high school built by DISD in recent years. Our work included a 1,000-ton central chilled water system, central hot water heating system and plumbing systems to serve this new school facility.

Project: Creekview High School
Location: Carrollton, Texas
Type: New High School
Description:

General Contractor: Turner Construction - Dallas, Texas This new 365,000 sq. ft. high school for the district employed a 1,200-ton central plant chilled water system, central hot water heating system and rooftop air handling units to serve the facility.

Project: A.C. New Middle School
Location: Balch Springs, Texas
Type: Expansion
Description:

General Contractor: Paul Pogue, LP - McKinney, Texas - For this existing school, we replaced the existing central plant with a new 350-ton chilled water system serving the existing and expanded facility.

Project: Allen Senior High School
Location: Allen, TX
Type: Expansion
Description:

General Contractor: Paul Pogue, LP - McKinney, Texas - At this 2,600 student facility we have served as mechanical contractor for the Phase 2 expansion, 525-ton absorption plant addition and the cafeteria expansion.

Project: Lewisville Elementary #38
Location: Dallas, Texas
Type: New School
Description:

General Contractor: Hunt Construction Group - Dallas, Texas - We served as mechanical contractor for this new 100,000 SF school that was served by a 250-ton chilled water central plant.

Project: Rockwall-Heath High School
Location: Rockwall, Texas
Type: New School
Description:

General Contractor: Paul Pogue, LP - McKinney, Texas - New 290,000 SF Senior High School that employs a 745-ton chilled water central plant.

Project: University of North Texas - Gateway Center
Location: Denton, Texas
Type: Convention and Dining Center
Description:

General Contractor: Austin Commercial, Inc. - Dallas, Texas - We provided an 1800-ton chilled water plant to serve this university's first-class convention and dining center.

© 2005 Berger Engineering Company